Long X Bridge Project Updates through 1/13/20
? Phase 1 dirt work has been completed, Phase 2 dirt work is approximately halfway completed and will resume inMarch 2020 come the spring thaw.? Drilled Shafts have been poured; Abutment 1 will be formed and poured over the drilled shafts in the spring.? Road Widening and Shoofly where the Wildlife crossing is to be constructed have been paved; construction of theWildlife Crossing will also begin in March 2020.? All structural H-Pile for the Long X Bridge have been driven/installed; H-Pile for support of the Wildlife crossing willbegin in March 2020.? Long X Bridge span 5 girders have been set; span 4 girders have been stockpiled on site, spans 1-4 will be set in thespring of 2020.? Work for winter is slowing down and wrapping up for the season. Work will recommence approximately March 1,2020, depending on temperatures and snowfall.? The complete bridge deck will be poured after girders for spans 1-4 have been set in the spring of 2020.? The Long X Bridge will be completed and open to traffic winter 2020.? Existing bridge will be demolished prior to June 2021.